Marcus Garvey Park Comfort Station Construction
-
100% complete
-
100% complete
-
66% complete
This project will construct a new comfort station and Little League building in Marcus Garvey Park.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: March 2015
Projected Completion Date:
February 2016
Completion Date:
April 2016
Procurement
Start Date: April 2016
Projected Completion Date:
December 2016
Completion
Date:
June 2017
Construction
Start Date: July 2017
Projected Completion Date:
January 2019
Adjusted Completion
Date:
March 2021
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
- Private
Location
Marcus Garvey Park
, Manhattan
18 Mount Morris Park West, between West 121st Street and West 122nd Street
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/26/2021