Marcus Garvey Park Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    14% complete

This project will construct a new comfort station and Little League building in Marcus Garvey Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: February 2016
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: December 2016
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: January 2019
Adjusted Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $2,575,000
Funding Sources:
  • Mayoral
  • State
  • Private

Location

Marcus Garvey Park , Manhattan
18 Mount Morris Park West, between West 121st Street and West 122nd Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/15/2018