Marcus Garvey Park Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    60% complete

This project will construct a new comfort station and Little League building in Marcus Garvey Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: February 2016
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: December 2016
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: January 2019
Adjusted Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $3,871,000
Funding Sources:
  • Mayoral
  • State
  • Private

Location

Marcus Garvey Park , Manhattan
18 Mount Morris Park West, between West 121st Street and West 122nd Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/05/2020