Frederick Johnson Park Tennis Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the tennis courts in Frederick Johnson Park.

Project Timeline

Design

Start Date: September 2010
Completion Date: February 2012

Procurement

Start Date: February 2012
Projected Completion Date: October 2012
Completion Date: October 2012

Construction

Start Date: March 2013
Projected Completion Date: March 2014
Completion Date: October 2013