St. Nicholas Playground North Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    92% complete

This project will reconstruct the comfort station at St. Nicholas North Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline


Start Date: August 2009
Projected Completion Date: August 2012
Completion Date: June 2015


Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: August 2016


Start Date: October 2016
Projected Completion Date: October 2017
Adjusted Completion Date: March 2018

Understand how we build parks.


Total Funding: $987,000
Funding Source: City Council


St. Nicholas Playground North , Manhattan
Adam Clayton Powell Jr. Boulevard and West 130th Street, Manhattan


Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 03/23/2018