St. Nicholas Playground North Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the comfort station at St. Nicholas North Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: August 2009
Projected Completion Date: August 2012
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: August 2016

Construction

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $910,000
Funding Source: City Council

Location

St. Nicholas Playground North , Manhattan
Adam Clayton Powell Jr. Boulevard and West 130th Street, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/15/2018