Riverside Park South Playground, Bikeway, and Plazas Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    98% complete

This project will construct a portion of Riverside Park South between West 65th Street and West 68th Street, including new plazas, play areas, lawns, volleyball courts, and a dog run, and it will reconstruct the bikeway between West 62nd Street and West 70th Street.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: May 2013
Projected Completion Date: December 2013
Completion Date: January 2015

Procurement

Start Date: January 2015
Projected Completion Date: October 2015
Completion Date: June 2016

Construction

Start Date: August 2016
Projected Completion Date: August 2018
Adjusted Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $21,084,000
Funding Sources:
  • Mayoral
  • Federal
  • Private

Location

Riverside Park South , Manhattan
Riverside Boulevard between West 62nd Street and West 70th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 06/05/2020