79th Street Boat Basin Dock A Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Dock A at the 79th Street Boat Basin in Riverside Park.

Project Timeline

Design

Start Date: March 2010
Projected Completion Date: March 2013
Completion Date: March 2014

Procurement

Start Date: March 2014
Projected Completion Date: December 2014
Completion Date: March 2015

Construction

Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $4,500,000
Funding Source: Mayoral

Location

Riverside Park, Manhattan
Riverside Park and 79th Street Boat Basin - Dock A

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/18/2017