Luther Gulick Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    33% complete

This project will reconstruct Luther Gulick Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2011
Projected Completion Date: June 2016
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: January 2019

Construction

Start Date: March 2019
Projected Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $10,454,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council
  • State
  • Federal

Location

Luther Gulick Park , Manhattan
Delancey Street between Willett Street and Columbia Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 09/13/2019