Stuyvesant Square Park East Section Fence and Sidewalk Reconstruction

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    82% complete 

This project will reconstruct the fence and sidewalks at Stuyvesant Square Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: August 2010
Projected Completion Date:December 2012
Completion Date: April 2013

Procurement

Start Date: April 2013
Projected Completion Date:January 2014
Completion Date: July 2014

Construction

Start Date: October 2014
Projected Completion Date:April 2016
Adjusted Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $4,090,000
Funding Sources:
  • City Council
  • Borough President

Location

Stuyvesant Square, Manhattan
Rutherford Place, Nathan D. Perlman Place, East 15th and East 17th Streets, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/13/2017