Peck Slip Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    69% complete

This project will reconstruct Peck Slip.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2017
Projected Completion Date: December 2018
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Completion Date: December 2019

Construction

Start Date: January 2020
Projected Completion Date: January 2021

Understand how we build parks.

Funding

Total Funding: $5,568,000
Funding Sources:
  • Mayoral
  • Federal

Location

Peck Slip , Manhattan
Peck Slip between Water Street and South Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/27/2020