Calvert Vaux Park Soccer Fields Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct two soccer fields in Calvert Vaux Park.

Project Timeline

Design

Start Date: April 2007
Projected Completion Date: September 2007
Completion Date: December 2007

Procurement

Start Date: December 2007
Projected Completion Date: September 2008
Completion Date: June 2008

Construction

Start Date: February 2009
Projected Completion Date: February 2010
Completion Date: October 2013

Understand how we build parks.

Funding

Total Funding: $17,047,000
Funding Source: Mayoral

Location

Calvert Vaux Park, Brooklyn
Shore Parkway between Bay 44th & Bay 49th Streets.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project