Coney Island Boardwalk Reconstruction Between Brighton 15th Street and Coney Island Avenue

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    100% complete 

This project will reconstruct the entrance at Brighton 15th Street and the boardwalk between Brighton 15th Street and Coney Island Avenue.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: November 2009
Projected Completion Date:June 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date:September 2014
Completion Date: August 2014

Construction

Start Date: November 2014
Projected Completion Date:May 2016
Completion Date: May 2016

Understand how we build parks.

Funding

Total Funding: $7,126,000
Funding Source:Grants

Last updated: 03/26/2017