NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Coney Island Boardwalk Reconstruction Between Brighton 15th Street and Coney Island Avenue

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the entrance at Brighton 15th Street and the boardwalk between Brighton 15th Street and Coney Island Avenue.

Project Timeline

Design

Start Date: November 2009
Projected Completion Date: June 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: August 2014

Construction

Start Date: November 2014
Projected Completion Date: May 2016
Completion Date: May 2016

Understand how we build parks.

Funding

Total Funding: $7,126,000
Funding Source: State

Last updated: 08/04/2017

Was this information helpful?