Coney Island Beach and Boardwalk Entrance Gardens Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct new, attractive entrances to the beach and boardwalk at Brighton 2nd Street and West 33rd Street featuring new accessible ramps, stairs, seating areas, paths, benches, fences, lighting, railing and plantings.

Project Timeline

Design

Start Date: March 2011
Completion Date: January 2012

Procurement

Start Date: January 2012
Projected Completion Date: October 2012
Completion Date: August 2012

Construction

Start Date: October 2012
Projected Completion Date: October 2013
Completion Date: April 2015

Understand how we build parks.

Funding

Total Funding: $1,978,000
Funding Source: State

Location

Coney Island Beach & Boardwalk , Brooklyn
Coney Island Boardwalk at Brighton 2nd Street and at West 33rd Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 09/29/2020