Coney Island Beach Entrance Garden Construction at Brighton 2nd and West 33rd Sts

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will create a new, attractive entrance to the beach and boardwalk at Brighton 2nd Street featuring new accessible ramps, stairs and seating areas. The project will include new paths, benches, fences, lighting, railing and plantings.

Project Timeline

Design

Start Date: March 2011
Completion Date: January 2012

Procurement

Start Date: January 2012
Projected Completion Date: October 2012
Completion Date: August 2012

Construction

Start Date: October 2012
Projected Completion Date: October 2013
Completion Date: April 2015

Understand how we build parks.

Funding

Total Funding: $2,276,000
Funding Source: State

Location

Coney Island Beach & Boardwalk, Brooklyn
Brighton 2nd and West 33rd Streets, Coney Island Beach and Boardwalk, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 06/23/2017