Brooklyn General Site Work (BG-711M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct tennis courts and basketball courts at various parks in Brooklyn.

Project Timeline

Design

Start Date: May 2011
Completion Date: September 2011

Procurement

Start Date: September 2011
Projected Completion Date: June 2012
Completion Date: November 2012

Construction

Start Date: December 2012
Projected Completion Date: June 2014
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $2,697,000
Funding Sources:
  • City Council
  • Private

Locations

  • Bensonhurst Park, Brooklyn
    Cropsey Avenue between 21 Avenue and Bay Parkway
  • Dean Playground, Brooklyn
    Dean To Bergen Sts Bet 6 and Carlton Avs
  • Hamilton Metz Field, Brooklyn
    Albany, E New York, Lefferts Avs
  • Manhattan Beach Park, Brooklyn
    Oriental Blvd. bet. Ocean Ave. and Mackenzie St.
  • McCarren Park, Brooklyn
    N. 12 St., Lorimer St., Manhattan Ave. bet. Bayard St. and Berry St. - Nassau Ave.
  • South Oxford Park, Brooklyn
    S. Oxford St. bet. Commos and Atlantic Ave.
  • (Non-Parks) Property in Brooklyn.
 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 06/23/2017