Brooklyn General Site Work (BG-711M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct tennis courts and basketball courts at various parks in Brooklyn.

Project Timeline

Design

Start Date: May 2011
Completion Date: September 2011

Procurement

Start Date: September 2011
Projected Completion Date: June 2012
Completion Date: November 2012

Construction

Start Date: December 2012
Projected Completion Date: June 2014
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $2,697,000
Funding Sources:
  • City Council
  • Private

Locations

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 12/15/2018