Banneker Playground and Tilden Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the comfort stations at Banneker Playground and Tilden Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: January 2019
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: November 2019
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: April 2023

Understand how we build parks.

Funding

Total Funding: $1,700,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/17/2021