Prospect Park Litchfield Villa Boiler and HVAC Systems Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the boiler and HVAC systems at the Litchfield Villa Annex in Prospect Park.

Project Timeline

Design

Start Date: June 2011
Completion Date: June 2012

Procurement

Start Date: June 2012
Projected Completion Date: March 2013
Completion Date: January 2014

Construction

Start Date: October 2014
Projected Completion Date: October 2015
Completion Date: December 2015