Canarsie Park Playground Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a playground in Canarsie Park.

Project Timeline

Design

Start Date: March 2011
Projected Completion Date: October 2011
Completion Date: December 2011

Procurement

Start Date: December 2011
Projected Completion Date: September 2012
Completion Date: October 2012

Construction

Start Date: October 2012
Projected Completion Date: October 2013
Completion Date: October 2013

Understand how we build parks.

Funding

Total Funding: $2,225,000
Funding Sources:
  • Borough President
  • City Council

Location

Canarsie Park , Brooklyn
Seaview Avenue and East 80th Street.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/18/2021