  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    34% complete

This project will reconstruct the roof at the Wyckoff House in M. Fidler/Wyckoff House Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2011
Projected Completion Date: April 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: May 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $451,000
Funding Source: State

Location

Fidler-Wyckoff House Park, Brooklyn
Ditmas Avenue and Clarendon Road, Brooklyn.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/23/2018