Wyckoff House Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof at the Wyckoff House in M. Fidler/Wyckoff House Park.

Project Timeline

Design

Start Date: June 2011
Projected Completion Date: April 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: May 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $380,000
Funding Source: State

Location

Fidler-Wyckoff House Park , Brooklyn
Ditmas Avenue and Clarendon Road

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 12/14/2018