Bill Brown Memorial Park Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    63% complete

This project will reconstruct the comfort station in Bill Brown Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline


Start Date: November 2011
Projected Completion Date: December 2012
Completion Date: October 2013


Start Date: October 2013
Projected Completion Date: June 2014
Completion Date: July 2014


Start Date: February 2015
Projected Completion Date: August 2016
Adjusted Completion Date: August 2018

Understand how we build parks.


Total Funding: $1,930,000
Funding Sources:
  • Mayoral
  • City Council


Bill Brown Playground , Brooklyn
Bedford Avenue and Avenue X to Avenue Y and 24th Street, Brooklyn


Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 03/16/2018