  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a 3.5-acre natural habitat for waterfowl by excavating existing fill material, re-grading steep slopes and creating inter-tidal zones. It will also include a new boat launch ramp, fencing, and plantings.

Project Timeline

Design

Start Date: November 2001
Projected Completion Date: October 2002
Completion Date: January 2009

Procurement

Start Date: January 2009
Projected Completion Date: October 2009
Completion Date: July 2011

Construction

Start Date: September 2011
Projected Completion Date: August 2012
Completion Date: August 2013

Understand how we build parks.

Funding

Total Funding: $2,850,000
Funding Sources:
  • Mayoral
  • City Council
  • State

Location

Calvert Vaux Park, Brooklyn
Shore Parkway near Bay 49th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project