Gravesend Park Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new comfort station at Gravesend Park.

Project Timeline

Design

Start Date: January 2012
Projected Completion Date: July 2013
Completion Date: September 2014

Procurement

Start Date: September 2014
Projected Completion Date: June 2015
Completion Date: August 2015

Construction

Start Date: November 2015
Projected Completion Date: April 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $2,026,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Gravesend Park , Brooklyn
18th Avenue between 56th Street and 57th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/05/2020