Ocean Parkway Malls Reconstruction, Shore Pkwy to Sea Breeze Ave

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct portions of the west side of the Ocean Parkway Malls.

Project Timeline

Design

Start Date: September 2011
Projected Completion Date: August 2012
Completion Date: September 2012

Procurement

Start Date: September 2012
Projected Completion Date: June 2013
Completion Date: April 2013

Construction

Start Date: May 2013
Projected Completion Date: May 2014
Completion Date: May 2014

Understand how we build parks.

Funding

Total Funding: $1,251,000
Funding Sources:
  • Borough President
  • City Council

Location

Ocean Parkway Malls , Brooklyn
Between Shore Parkway and Sea Breeze Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/05/2022