Leif Ericson Park Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a comfort station in Leif Ericson Park.

Project Timeline

Design

Start Date: July 2010
Projected Completion Date: May 2013
Completion Date: April 2013

Procurement

Start Date: April 2013
Projected Completion Date: January 2014
Completion Date: September 2013

Construction

Start Date: November 2013
Projected Completion Date: March 2015
Completion Date: December 2015

Understand how we build parks.

Funding

Total Funding: $1,327,000
Funding Sources:
  • Borough President
  • City Council

Location

Leif Ericson Park, Brooklyn
Bounded by 66th and 67th Streets, and 8th and 9th Avenues, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/20/2017