Gravesend Park Playground and Court Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will demolish the hockey rink and expand the playground and reconstruct the court area and ballfields in Gravesend Park.

Project Timeline

Design

Start Date: September 2009
Projected Completion Date: November 2012
Completion Date: April 2014

Procurement

Start Date: April 2014
Projected Completion Date: January 2015
Completion Date: December 2014

Construction

Start Date: May 2015
Projected Completion Date: November 2016
Completion Date: October 2016

Understand how we build parks.

Funding

Total Funding: $5,321,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Gravesend Park , Brooklyn
18th Avenue, 55th Street, 19th Avenue, 58th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project