Sunset Park Spray Shower Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will create an attractive and accessible spray shower in the footprint of the existing wading pool. The new spray shower will feature vertical water spray elements of varying heights, a central waterfall, ground sprays for toddlers, touch activated bollards, stainless steel play drums, bench seating and decorative pavements. New trees, ornamental plantings, fencing and a drinking fountain will also be included.

Project Timeline

Design

Start Date: September 2010
Projected Completion Date: May 2012
Completion Date: June 2012

Procurement

Start Date: June 2012
Projected Completion Date: March 2013
Completion Date: May 2013

Construction

Start Date: September 2013
Projected Completion Date: September 2014
Completion Date: October 2014

Understand how we build parks.

Funding

Total Funding: $1,112,000
Funding Sources:
  • Mayoral
  • City Council

Location

Sunset Park , Brooklyn
7th Avenue between 41st and 44th Streets in Sunset Park, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/15/2019