Chelsea Recreation Center Storefront Entry System Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the storefront entry system at the Chelsea Recreation Center.
Project Update: A date has been set for construction to begin.
Project Timeline
Design
Start Date: April 2022
Projected Completion Date:
November 2022
Completion Date:
June 2022
Procurement
Start Date: May 2022
Projected Completion Date:
October 2022
Completion
Date:
May 2022
Construction
Start Date:
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Chelsea Recreation Center
, Manhattan
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 08/11/2022