Central Park Rumsey Playhouse Electrical Repairs

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

Electrical Repairs

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: March 2022
Projected Completion Date: September 2022
Completion Date: April 2022

Procurement

Start Date: March 2022
Projected Completion Date: August 2022
Completion Date: January 2022

Construction

Start Date: April 2022
Projected Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $42,000
Funding Source: Mayoral

Location

Central Park , Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/25/2022

Was this information helpful?