Crotona Parkway Malls Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct pavements at Crotona Parkway Malls.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: April 2022
Projected Completion Date: October 2022
Completion Date: June 2022

Procurement

Start Date: April 2022
Projected Completion Date: September 2022
Completion Date: March 2022

Construction

Start Date: July 2022
Projected Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $558,000
Funding Source: Mayoral

Location

Crotona Parkway Malls , Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 09/26/2022