Cooney Grauer Field Lighting Reconstruction
-
30% complete
-
5% complete
-
0% complete
This project will reconstruct the ballfield lighting at Cooney Grauer Field with energy-efficient LED fixtures.
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
NYC Parks staff members are currently reviewing the scope of the work order.
Project Timeline
Design
Start Date: January 2022
Projected Completion Date:
June 2022
Procurement
Start Date: January 2022
Projected Completion Date:
June 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Cooney Grauer Field
, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 05/26/2022