North 5th Street Pier and Park Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pavement at North 5th Street Pier and Park.

Project Timeline

Design

Start Date: September 2021
Projected Completion Date: June 2022
Completion Date: December 2021

Procurement

Start Date: October 2021
Projected Completion Date: March 2022
Completion Date: March 2022

Construction

Start Date: November 2021
Projected Completion Date: February 2022
Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $272,000
Funding Source: Private

Location

North 5th Street Pier and Park , Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/01/2022