Calvert Vaux Park Ballfield Lighting Reconstruction

  • Design
    30% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the ballfield lighting at Calvert Vaux Park with energy-efficient LED fixtures.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

NYC Parks staff members are currently reviewing the scope of the work order.

Project Timeline

Design

Start Date: October 2021
Projected Completion Date: October 2022

Procurement

Start Date: December 2021
Projected Completion Date: May 2022

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Calvert Vaux Park , Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/20/2022