Mahoney Playground Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the synthetic turf field at Mahoney Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: July 2021
Projected Completion Date: August 2022
Completion Date: April 2022

Procurement

Start Date: September 2021
Projected Completion Date: February 2022
Completion Date: April 2022

Construction

Start Date:

Understand how we build parks.

Funding

Total Funding: $462,000
Funding Source: Mayoral

Location

Mahoney Playground , Staten Island

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/01/2022