Columbus Park Synthetic Turf Field Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the synthetic turf field at Columbus Park.
Project Update: A date has been set for construction to begin.
Project Timeline
Design
Start Date: July 2021
Projected Completion Date:
August 2022
Completion Date:
April 2022
Procurement
Start Date: September 2021
Projected Completion Date:
February 2022
Completion
Date:
April 2022
Construction
Start Date: June 2022
Projected Completion Date:
July 2022
Understand how we build parks.
Funding
Funding Source: Mayoral