Bartow Pell Mansion Interior and Window Reconstruction

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    98% complete 

This project will reconstruct portions of the Bartow-Pell Mansion including plastering and window repainting.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: April 2008
Projected Completion Date:September 2012
Completion Date: December 2014

Procurement

Start Date: December 2014
Projected Completion Date:September 2015
Completion Date: December 2014

Construction

Start Date: December 2014
Projected Completion Date:December 2015
Adjusted Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayor
  • City Council
  • Borough President

Location

Pelham Bay Park, Bronx
Shore Road in Pelham Bay Park

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 01/13/2017