Colucci Playground Seating Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct new fencing, gates, planting beds, benches, pavements, and a water supply system in Colucci Playground.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: June 2015
Completion Date: July 2015

Procurement

Start Date: July 2015
Projected Completion Date: April 2016
Completion Date: July 2016

Construction

Start Date: August 2016
Projected Completion Date: August 2017
Completion Date: August 2017

Understand how we build parks.

Funding

Total Funding: $693,000
Funding Source: City Council

Location

Colucci Playground , Bronx
Wilkinson Avenue between Hutchinson River Parkway East and Mayflower Avenue

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 06/28/2022