Raymond Bush Playground Drainage Line Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the main water and sewer drainage line at Raymond Bush Playground.
Project Update: A date has been set for construction to begin.
Project Timeline
Design
Start Date: July 2021
Projected Completion Date:
March 2022
Completion Date:
February 2022
Procurement
Start Date: August 2021
Projected Completion Date:
January 2022
Completion
Date:
January 2022
Construction
Start Date: May 2022
Projected Completion Date:
August 2022