Astoria Park Field House Roof Reconstruction

  • Design
    30% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the roof of the field house in Astoria Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

The budget approval documents are currently under review by the NYC Office of Management and Budget.

Project Timeline

Design

Start Date: April 2021
Projected Completion Date: April 2022

Procurement

Start Date: April 2021
Projected Completion Date: September 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Astoria Park , Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/24/2021

Was this information helpful?