Sunset Park Recreation Center Telecommunication Lines Reconstruction

  • Design
    30% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the telecommunication lines to Sunset Park Recreation Center.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

The budget approval documents are currently under review by the NYC Office of Management and Budget.

Project Timeline

Design

Start Date: November 2020
Projected Completion Date: May 2021

Procurement

Start Date: March 2021
Projected Completion Date: August 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Sunset Park , Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/24/2021