Metropolitan Recreation Center Fire Alarm System Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the fire alarm system at Metropolitan Recreation Center.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: Design is complete.

NYC Parks staff members are currently reviewing the scope of the work order.

Project Timeline

Design

Start Date: October 2019
Projected Completion Date: January 2021
Completion Date: January 2021

Procurement

Start Date: February 2021
Projected Completion Date: July 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Metropolitan Recreation Center , Brooklyn

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 04/16/2021