Amelia Gorman Park Retaining Wall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct a section of retaining wall in Amelia Gorman Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: November 2019
Projected Completion Date: June 2021
Completion Date: June 2022

Procurement

Start Date: December 2020
Projected Completion Date: May 2021
Completion Date: October 2021

Construction

Start Date:

Understand how we build parks.

Funding

Total Funding: $2,163,000
Funding Source: Mayoral

Location

Amelia Gorman Park , Manhattan

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 07/05/2022