St. Nicholas Park Rockface Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the rockface along St. Nicholas Avenue between West 138th Street and West 139th Street in St. Nicholas Park.

Project Timeline

Design

Start Date: November 2019
Projected Completion Date: December 2020
Completion Date: March 2021

Procurement

Start Date: December 2020
Projected Completion Date: May 2021
Completion Date: October 2021

Construction

Start Date: January 2022
Projected Completion Date: April 2022
Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $966,000
Funding Source: Mayoral

Location

St. Nicholas Park , Manhattan

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 05/25/2022