Columbus Park Synthetic Turf Field Reconstruction

  • Design
    5% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the synthetic turf field at Columbus Park.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

The budget approval documents are currently under review by the NYC Office of Management and Budget.

Project Timeline

Design

Start Date: March 2020
Projected Completion Date: September 2020

Procurement

Start Date: March 2020
Projected Completion Date: August 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source:

Location

Columbus Park , Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project