Astoria Park Field House Restrooms Reconstruction
-
30% complete
-
85% complete
-
0% complete
This project will reconstruct the public restrooms in the field house at Astoria Park.
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
The work order has been sent to the Comptroller's Office for registration.
Project Timeline
Design
Start Date: November 2019
Projected Completion Date:
August 2020
Procurement
Start Date: March 2020
Projected Completion Date:
August 2020
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source:
Location
Astoria Park
, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 02/26/2021