Cunningham Park Redwood Playground Comfort Station Sewer Line Reconstruction

  • Design
    5% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the comfort station sewer line at Redwood Playground in Cunningham Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

NYC Parks has received budget approval and is finalizing the work order documentation.

Project Timeline

Design

Start Date: January 2020
Projected Completion Date: June 2020

Procurement

Start Date: March 2020
Projected Completion Date: August 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Cunningham Park , Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/19/2020