Captain John McKenna IV Park Water Line Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the water line to Captain John McKenna IV Park.

Project Timeline

Design

Start Date: January 2020
Projected Completion Date: June 2021
Completion Date: September 2020

Procurement

Start Date: March 2020
Projected Completion Date: August 2020
Completion Date: December 2020

Construction

Start Date: March 2021
Projected Completion Date: July 2021
Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $200,000
Funding Sources:
  • Mayoral
  • City Council

Location

Captain John McKenna, IV Park , Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 09/30/2022

Was this information helpful?