Captain John McKenna IV Park Water Line Reconstruction

  • Design
    5% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the water line to Captain John McKenna IV Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

NYC Parks has received budget approval and is finalizing the work order documentation.

Project Timeline

Design

Start Date: January 2020
Projected Completion Date: June 2021

Procurement

Start Date: March 2020
Projected Completion Date: August 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • City Council