Mosholu Parkway WWI Monument Lighting System Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a lighting system for Mosholu Parkway WWI Monument.

Project Timeline

Design

Start Date: November 2010
Projected Completion Date: January 2012
Completion Date: February 2012

Procurement

Start Date: February 2012
Projected Completion Date: October 2012
Completion Date: December 2012

Construction

Start Date: March 2013
Projected Completion Date: August 2013
Completion Date: September 2013

Understand how we build parks.

Funding

Total Funding: $89,000
Funding Source: City Council

Location

Mosholu Parkway , Bronx
Mosholu Parkway at Marion & Hull Avenues

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project