Richman (Echo) Park Maintenance Shed Roof Reconstruction

  • Design
    80% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the maintenance shed roof at Richman (Echo) Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: Parks staff members are reviewing construction documents for this project.

NYC Parks staff members are currently reviewing the scope of the work order.

Project Timeline

Design

Start Date: September 2019
Projected Completion Date: March 2020

Procurement

Start Date: March 2020
Projected Completion Date: August 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Richman (Echo) Park , Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/19/2020