Silver Lake Park Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct paths and pavement in the southern half of Silver Lake Park.

Project Timeline

Design

Start Date: August 2019
Projected Completion Date: June 2020
Completion Date: March 2020

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Construction

Start Date: April 2021
Projected Completion Date: October 2021
Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $950,000
Funding Source: Mayoral

Location

Silver Lake Park , Staten Island

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/20/2022