Claremont Park Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pathways and pavement at Claremont Park.

Project Timeline

Design

Start Date: August 2019
Projected Completion Date: June 2020
Completion Date: April 2020

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: March 2020

Construction

Start Date: September 2020
Projected Completion Date: June 2021
Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $1,445,000
Funding Source: Mayoral

Location

Claremont Park , Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 09/29/2022

Was this information helpful?