Claremont Park Pavement Reconstruction

  • Design
    30% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct pathways and pavement at Claremont Park.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

The budget approval documents are currently under review by the NYC Office of Management and Budget.

Project Timeline

Design

Start Date: August 2019
Projected Completion Date: June 2020

Procurement

Start Date: September 2019
Projected Completion Date: February 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Claremont Park , Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/08/2019