Claremont Park Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct pathways and pavement at Claremont Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: August 2019
Projected Completion Date: June 2020
Completion Date: April 2020

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: March 2020

Construction

Start Date:

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Claremont Park , Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 08/07/2020