Liberty Pool Deck Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the pool deck at Liberty Pool.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: September 2019
Projected Completion Date: September 2020
Completion Date: September 2021

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: September 2021

Construction

Start Date: October 2021
Projected Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $1,301,000
Funding Source: Mayoral

Location

Detective Keith L Williams Park , Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/25/2022

Was this information helpful?