Mt. Hope Garden Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    39% complete

This project will reconstruct the retaining walls and play areas at Mt. Hope Garden.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2014
Projected Completion Date: October 2015
Completion Date: July 2015

Procurement

Start Date: July 2015
Projected Completion Date: April 2016
Completion Date: September 2016

Construction

Start Date: February 2017
Projected Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $3,750,000
Funding Sources:
  • Mayoral
  • City Council

Location

Mount Hope Garden, Bronx
West side of Creston Avenue between East Burnside Avenue East 179th Streets

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 02/22/2018