Dry Dock Pool Deck Reconstruction

  • Design
    5% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the pool deck at Dry Dock Pool.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

NYC Parks staff members are currently reviewing the scope of the work order.

Project Timeline

Design

Start Date: September 2019
Projected Completion Date: September 2020

Procurement

Start Date: September 2019
Projected Completion Date: February 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral