Dry Dock Pool Deck Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pool deck at Dry Dock Pool.

Project Timeline

Design

Start Date: September 2019
Projected Completion Date: September 2020
Completion Date: September 2021

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: September 2021

Construction

Start Date: November 2021
Projected Completion Date: June 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $1,200,000
Funding Source: Mayoral

Location

Dry Dock Playground , Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/05/2022

Was this information helpful?